Blue HorizonProjects

Planning · 6 min read

How Long Does a New Build Take?

By Blue Horizon Projects · · 6 min read

Illustrative photograph for the article How Long Does a New Build Take?

Clients usually ask about construction time. The full journey from first conversation to keys is roughly double that, and planning for the real number avoids a lot of frustration.

The short answer

For a custom home on the Central Coast, expect 18 to 30 months end to end: 4 to 9 months of design and approvals, then 10 to 16 months on site.

Full timeline

StageTypical duration
Consultation and feasibility2 – 4 weeks
Concept and design development8 – 16 weeks
Engineering, BASIX and documentation4 – 8 weeks
Approval3 – 24 weeks
Construction40 – 70 weeks
Practical completion and handover2 – 4 weeks

What extends a program

  • Rock, poor soil classification or unexpected site conditions
  • DA referrals and additional information requests
  • Long-lead items such as windows, joinery and imported tile
  • Design changes made after documentation is complete
  • Sustained wet weather during early trades
A realistic program given honestly at the start is worth more than an optimistic one that erodes month by month.

What you can control

Decisions. Confirm your brief before documentation, lock selections before construction, and resist changes once framing is up. Clients who do this consistently finish closest to program.

Frequently asked

Can you build faster than that?
Occasionally, on simple sites with a straightforward CDC pathway and no long-lead selections. We'd rather quote a program we can hold to.
When should we start if we want to move in by a certain date?
Work back two and a half years for a custom home, and about eighteen months for a second storey addition.